Researched BPOs/BPCs not giving full ME reduction

Author
Rin Nagamori
Center for Advanced Studies
Gallente Federation
#1 - 2014-10-26 08:19:06 UTC
While trying to decide which rigs to manufacture today, I noticed that several BPOs/BPCs were not factoring the full 10% reduction in materials usage when calculating required materials for production. For example:

The Large Capacitor Control Circuit I requires a base amount of 20 Melted Capacitor Consoles for an individual rig. For a production run of 100, then, the base amount is 2000, which means that when you factor the 10% ME on the blueprint, you should only need 1800. Instead, the industry window returns the amount of 1980, meaning that the actual percentage reduced is just 1%.

This is not an isolated incident, either. A casual examination of my other blueprints suggests that a good number of them are also returning erroneous material requirements for at least some of the materials required.

Am I the only person who noticed this?
Ria Nieyli
Nieyli Enterprises
When Fleets Collide
#2 - 2014-10-26 08:45:09 UTC  |  Edited by: Ria Nieyli
Rin Nagamori wrote:
While trying to decide which rigs to manufacture today, I noticed that several BPOs/BPCs were not factoring the full 10% reduction in materials usage when calculating required materials for production. For example:

The Large Capacitor Control Circuit I requires a base amount of 20 Melted Capacitor Consoles for an individual rig. For a production run of 100, then, the base amount is 2000, which means that when you factor the 10% ME on the blueprint, you should only need 1800. Instead, the industry window returns the amount of 1980, meaning that the actual percentage reduced is just 1%.

This is not an isolated incident, either. A casual examination of my other blueprints suggests that a good number of them are also returning erroneous material requirements for at least some of the materials required.

Am I the only person who noticed this?


The researched blueprint is showing you the amount of Melted Capacitor Consoles you need AFTER the reduction. The base amount is 22 MCC on a 0% ME blueprint, 10% ME research gives you 19.8 MCC per use, which gets rounded to 20 for a single run. If you do 100 runs, you fully benefit from the reduction, since it's calculated for the whole batch, hence 1980 required parts.
Rin Nagamori
Center for Advanced Studies
Gallente Federation
#3 - 2014-10-26 09:14:29 UTC
You are indeed correct. I must have missed some patch notes/ dev post somewhere, then. Anyway, thanks for the reply.